Project Timeline

  • 2008

    The Badgingarra Wind Farm was approved by the Shire of Dandaragan. A portion of the wind farm was approved over Parron Place.

  • 2016

    Parron Developments installed a meteorological mast that confirmed Parron Place is home to a world class wind resource.

  • May 2024

    Parron Developments partners with Atmos Renewables to develop the Parron Wind Farm.

  • Q4 2024

    Development Approval submitted. State and Federal Environmental Approvals also submitted.

  • December 2024

    Development Approval – 79 Wind Turbines

    In December, the Shire of Dandaragan approved the construction and operation of the Parron Wind Farm (PWF) and associated infrastructure.

    Attachment: Development Approval

  • February 2025

    Heritage Surveys

    PWF and the Yued Aboriginal Corporation have entered into a Heritage Protection Agreement and in February, Heritage Surveys were conducted on the proposed wind farm site. We have adjusted the proposed turbine layout based on Yued feedback about waterways and vegetation.

  • March 2025

    Western Australia Environmental Approval

    The Environmental Protection Authority (EPA) advised formal assessment of the Parron Wind Farm under Part IV of the Environmental Protection Act 1986 is not warranted.

    Attachment: EPA Chair Determination – Parron Wind Farm

  • May 2025

    Federal Environmental Approval

    The Federal Environmental regulator the Department of Climate Change, Energy, Environment and Water advised that our application “to construct and operate Parron Wind Farm and associated infrastructure” was not a controlled action.

    Attachment: Notice EPBC - Parron Wind Farm

  • 2025 – Q1 2026

    Pre-construction earthworks scheduled to begin, including access tracks and site preparation.

  • 2026–2028

    Main construction phase, including turbine installation and grid connection works.

  • 2028–2058

    Operation of the Parron Wind Farm, generating clean energy for the grid.

  • Post 2058

    Planned decommissioning of the Parron Wind Farm following its operational lifespan.

Approvals & Notifications

  • Notice of Public Advertisement of Planning Proposal

    Note: Link now closed on the Shire of Dandaragan website

  • Development Approval

    Notice of Determination issued 6 January 2025

  • EPA Chair Determination

    Issued 28 March 2025

  • Dept. of Climate Change, Energy, the Environment and Water

    Notification of referral decision – not controlled action

Project Updates

In the coming weeks, you may start to see information about our project - we look forward to hearing community feedback and sharing our vision for the Parron Wind Farm.

Register here to receive project updates.